VATMAL: Israel’s Fast Track for Planning New Neighbourhoods

The VATMAL is a national committee that approves large housing plans on a fast track. For anyone who holds land or is considering buying, entering the track is a sign of progress, but it is not yet an approval.

  • ERRA Team
  • Updated
  • 7 min read
VATMAL: Israel’s Fast Track for Planning New Neighbourhoods

The bottom line

Declaring a VATMAL compound is not the approval of a plan. The risk falls only when the plan is deposited, passes objections and is approved, and what decides things for the landowner is the allocation table.

164
plans approved at the VATMAL by the end of 2025
472
thousand housing units in the approved plans
13
months on average to approve a plan in 2025

What the VATMAL is

VATMAL is the Hebrew acronym for the National Committee for Planning and Building of Preferred Housing Areas. It was set up in 2014, under a law meant to increase the supply of apartments quickly.

On the regular track a plan moves between a local committee and a district committee. At the VATMAL one committee handles the whole process, and the law sets a deadline for each stage.

Preferred housing area
An area the government has declared, so that its plan is promoted at the VATMAL. The declaration opens the process, and it is not the approval of a plan.
Which plans enter
Large plans, usually at least 750 housing units. Since 2017 the track has also been open to private land with multiple owners and to urban renewal (pinui-binui).
Temporary order
The law is temporary. In July 2026 the Knesset extended it by one year, with limits on the track on state land. It applies to plans received by the committee by 9 August 2027.

The stages of the track

The law’s clock starts only when the plan is submitted and received by the committee. The preparation stage before that is not counted.

  1. 1
    Declaration

    The government declares a preferred housing area. At this stage there is no plan yet.

  2. 2
    Preparing and submitting the plan

    A planning team prepares a drawing, provisions, and environmental, transport and infrastructure studies.

  3. 3
    Deposit discussion

    The committee discusses whether to deposit the plan for public review.

    Within 45 working days
  4. 4
    Objections

    The public can file objections from the day of publication.

    60 days
  5. 5
    Investigator and subcommittee

    An investigator examines the objections and makes recommendations, and the subcommittee decides.

    30 + 30 working days
  6. 6
    Decision

    The committee approves, changes or rejects the plan.

    Up to 24 months from submission
  7. 7
    After approval

    Reparcellation, infrastructure development and building permits. Even after approval, years pass before building.

The VATMAL in numbers

The figures are from the VATMAL’s activity report for 2025.

FigureHow manyHousing units
Areas declared since 2014225
Plans approved by the end of 2025164About 472 thousand
Plans approved in 20251863,427
Plans being handled at the end of 202558About 228 thousand
Urban renewal, cumulative4767,901
Land with multiple owners, cumulative424,241

The last row matters for owners of private land: of the 164 plans approved, only 4 are on the track for land with multiple owners. In 2025, 3 new areas were declared on this track.

How much certainty there is at each stage

The further the plan advances, the more is known, and the planning risk falls.

StageWhat is already knownPlanning risk
DeclarationThe boundaries of the area, and an intention to planHigh
Planning and studiesFirst alternatives, with no binding documentHigh
DepositA drawing and provisions, and sometimes allocation tables tooMedium
After objectionsMost of the barriers have already been discussedLower
ApprovalThe rights have been set in the planA risk of time and execution remains

Why plans get stuck

Even on a fast track there are barriers. These are the five that recur.

  • Soil and groundwater contaminationIn the Apollonia plan in Herzliya, the Supreme Court cancelled the deposit and the approval and sent the plan back for planning, because no risk survey for contamination had been carried out.

  • Open areas and natural assetsObjections and petitions by residents and environmental organisations can delay a plan or reduce it.

  • Transport and infrastructureA large neighbourhood needs a solution for roads, water and sewage. Without one, the scale of the plan can shrink.

  • Multiple ownersOn private land with many owners, the reparcellation is more complex, and each owner receives according to the allocation table.

  • The law itselfThe track is temporary. The law applies only to plans received by the committee by 9 August 2027, and what happens afterwards depends on a further extension.

A plan that stopped at the VATMAL is not always cancelled. Sometimes it continues on another track, for example at the district committee, and then the timetable changes.

What to check before buying land in a VATMAL compound

  1. 01The plan number and status. Declaration, preparation, deposit or approval. Check on the Planning Administration’s planning information site (MAVAT).
  2. 02The blue line. Whether the parcel is inside the plan boundary, by block and parcel.
  3. 03The proposed use. Housing, employment, a road, a park or public buildings.
  4. 04Reparcellation. Whether the plan includes such a mechanism, and what the allocation and balancing tables say.
  5. 05Studies and barriers. Soil, environmental, drainage and transport surveys, and the objections that were filed.
  6. 06The history of the compound. Whether there were earlier plans that stopped or were replaced.

On reparcellation there is a full article on the site. On the other checks: the guide to buying land.

When to enter: three approaches

WhenAdvantageRisk
Early: after the declarationA lower priceThe plan can change, be delayed or not advance
In the middle: active planningThere are already documents and studiesStill before deposit and objections
Late: after the depositThe plan is clearerA higher price

No stage suits everyone. The choice depends on the time you have and the risk you are willing to take. For a comparison with an apartment: Land or an apartment.

An example: west Gedera

Compound 8 in Gedera is being promoted at the VATMAL under plan TAMAL 3011. The compound was declared a preferred housing area in January 2024, and the declaration was expanded in June 2026. As of November 2026 the plan has not yet been deposited.

The details are in Compounds 2, 7, 8 and 9 in Gedera, in the timeline Gedera 2015–2035 and on the project page.

Frequently asked questions

What is the VATMAL?

The National Committee for Planning and Building of Preferred Housing Areas. One committee that approves large housing plans on a fast track.

Does declaring a VATMAL compound mean the plan will be approved?

No. The declaration opens the process. After it come preparing the plan, deposit, objections and a decision, and the plan can change or not advance.

How long does it take to approve a plan at the VATMAL?

The law gives the committee up to 24 months from the submission of the plan. In 2025 the average was about 13 months. The preparation stage before submission is not included in this time.

Does the VATMAL also handle private land?

Yes. Since 2017 the track has also included private land with multiple owners. By the end of 2025, 4 plans had been approved on it, with 24,241 housing units.

Until when is the law in force?

The law is a temporary order. After the extension of July 2026 it applies to plans received by the committee by 9 August 2027.

Where do you check what stage a plan is at?

On the Planning Administration’s planning information site (MAVAT), by plan number or by block and parcel.

Summary

The VATMAL shortens the road to the approval of a plan, but it does not remove the risk. Before buying, check what stage the plan is at, where the parcel is inside the blue line, and what is expected in the allocation table. The information in this article is general and is not legal, appraisal or investment advice.

Further reading and tools

Articles

Pages

Sources

  1. 01Planning Administration: VATMAL activity report for 2025 (Hebrew)
  2. 02Law for the Promotion of Construction in Preferred Housing Areas (Temporary Order), 5774-2014 (Hebrew)
  3. 03Nadlan Center: the Interior Committee approved extending the VATMAL’s activity, 9.7.2026 (Hebrew)
  4. 04Ynet: the Knesset approved extending the VATMAL law by a year, with limits (Hebrew)
  5. 05Globes: the Supreme Court sent the Apollonia plan back for planning (Hebrew)
  6. 06Planning Administration: about the VATMAL (Hebrew)
  7. 07MAVAT: finding plans (Hebrew)

Written by

ERRA Team

Last updated: 21.11.2026

Share

More articles

All articles

Need us to make an appointment for you? Talk with us!

The Israeli Real Estate market is in continuous momentum and prices continue to rise from moment-to-moment. Let us match you with the right investment for you.

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.