- 131
- local committees in the State Comptroller's audit
- 22
- of them are independent committees
- 58.5
- months on average to approve a plan in the Central District Committee
The hierarchy
- The National Planning and Building Council
- Approves national outline plans, such as TAMA 35, and sets policy. It does not grant rights to a specific parcel, but marks where development is allowed and where land is preserved.
- Special national committees
- VATMAL approves large housing plans on a fast track, and the National Infrastructure Committee (VATAL) approves national infrastructure such as roads and railways. On VATMAL: VATMAL.
- The District Committee
- Prepares the district outline plan, approves comprehensive outline plans, and most of the plans that change designation from agricultural to residential. For an investor in agricultural land, this is usually the committee that decides.
- The local or regional committee
- Issues building permits, approves smaller plans, collects the betterment levy and pays compensation under Section 197. A regional committee serves several local authorities.
Amendment 101: powers moved down
In 2014 Amendment 101 to the Planning and Building Law was enacted. It transferred powers from the District Committees to the local committees, and set that a decision on a plan within the power of a District Committee would be made within 18 months of its submission. A local committee that meets the conditions receives certification as an independent committee, with more powers.
In practice the change is slow. According to a State Comptroller report from 2021, six years after the amendment only 22 out of 131 local committees had been certified as independent, and approving a plan in the Central District Committee took 58.5 months on average, close to five years. This is the order of magnitude to assume when calculating the time for a change of land designation.
How a plan advances
- 1Submission and intake
The plan is submitted to the competent institution, which checks that it is complete.
- 2Deposit hearing
The committee decides whether to deposit the plan, sometimes with conditions.
- 3Deposit and objections
The plan is published to the public, and anyone harmed by it can file an objection by the set date. This is the stage at which landowners can have an influence.
- 4Approval and entry into force
After the objections are heard, the plan is approved and published in Reshumot (the Official Gazette). From that day the deadlines for compensation claims run.
- 5Building permit
At the local committee, according to the detailed plan. This is usually where the betterment levy is paid.
Where to turn when you disagree
ObjectionTo the institution that deposited the plan, by the date set in the deposit notice. Anyone who did not object in time will find it hard to change things afterwards.
District Appeals CommitteeOn decisions of the local committee on plans and permits.
Appeals Committee for Compensation and Betterment LevyOn a betterment levy assessment and on the rejection of a claim under Section 197. Details: Compensation under Section 197.
Administrative Affairs CourtOn decisions of the appeals committees and on decisions of the planning institutions, mainly on legal questions.
Checklist: who is handling your land
- 01Which planning area is the parcel in? A city's local committee or a regional committee.
- 02Is the committee independent? This affects what it can approve on its own.
- 03Who is promoting the plan in the area? The municipality, the Planning Administration, the Israel Land Authority (ILA) or the landowners.
- 04Which institution is it being heard in? Local, district or VATMAL. This determines the timetable.
- 05What stage is it at? Submission, deposit, objections or entry into force.
FAQ
Who approves a change of designation from agricultural to residential?
In most cases the District Committee. In large housing plans that were declared preferred housing compounds, VATMAL.
How long does it take to approve a plan?
The law sets a target of 18 months for a decision in the District Committee. In practice, in the Central District the average was close to five years, according to the State Comptroller.
Can you object to a plan after it has been approved?
After approval an objection can no longer be filed. You can claim compensation if you were harmed, or turn to the court on legal questions.
Summary
Anyone investing in land needs to know who decides about it: which committee is handling the plan, what stage it is at, and when it is possible to have an influence. The actual time frames are longer than the targets in the law, and it is worth assuming them in advance. The information in this article is general and is not legal advice.
Further reading and tools on the site
Articles
- TAMA 35
- Comprehensive Outline Plan
- VATMAL
- Change of land designation: the 7 stages
- How to check land and plans yourself
Tools and pages
Sources