Converting Agricultural Land to Building Land

A comprehensive guide to the stages, timelines, and price increases

1/8

Overview

Total Profit Potential

1,200%-500%

over the base agricultural price

Process Time

24-3.6

years to completion

Main Stages

8

critical development stages

2/8

Price Increase Over Time

100%
Agricultural land
300-500%
Change of land designation
600-800%
District plan (TAMAM) ready
900-1,200%
District plan deposited
1,500-2,000%
District plan approved
2,500-3,000%
Levies paid
4,000-5,000%
Ready to build
3/8

Stages 1-2: Agricultural Land and Change of Land Designation

Time: 2.4-4.8 years

Agricultural land

100%

Starting point

←

Change of land designation

500%-300%
+400%-200%

Submitting an application

Application to the local/district committee

Multidisciplinary review

Environmental and transportation assessments

Public participation

Period for comments and objections

Designation approval

Final decision on the change

4/8

Stages 3-4: District Plan Preparation and Deposit

District plan deposited

1200%-900%
+50%

Time: 7.2 months-1.2 years

←

District plan (TAMAM) ready

800%-600%
+60%-20%

Time: 1.2-2.4 years

Time Distribution - District Plan Preparation Stage

20%
Up to a year
50%
1-2 years
25%
2-3 years
5%
Over 3 years

Detailed planning

Building rights and infrastructure

Impact assessments

Transportation and environment

Official Deposit

Public notice - 60 days

Handling Objections

Review of public comments

5/8

Stages 6-5: District Outline Plan (TAMAM) Approval and Reparcellation

District plan approved

2000%-1500%
+67%

Time: 7.2-3.6 months

←

Reparcellation

2500%-2000%
+33%-25%

Time: 7.2 months-1.2 years

Success Rates by Planning Stage

85%
District plan approved
95%
Reparcellation
75%
No delays
65%
On expected schedule

Final Approval

Local committee decision

Surveys

Precise documentation of boundaries

Land Registry (Tabu) Registration

Updating purchase rights

Division into Parcels

Creation of building plots

6/8

Stages 8-7: Levies and Infrastructure

Levies paid

3000%-2500%
+25%-20%

Time: 7.2-3.6 months

←

Infrastructure ready

4500%-3500%
+50%-40%

Time: 2.4-1.2 years

Breakdown of Levy Costs (of Land Value)

25-40%
Betterment levy (hetel hashbacha)
15-25%
Development levies
10-20%
Water infrastructure
5-15%
Electricity and communications

Betterment levy (hetel hashbacha)

50% of the increase in land value

Development levies

Roads, drainage, public services

Water and sewage infrastructure

Connection to municipal networks

Electricity and communications

Energy and communications infrastructure

7/8

Final Stage: Ready to Build

Ready to build

5000%-4000%
+14%-11%

Time: 7.2-3.6 months

Total time for the full process

10%
3.6-6 years
35%
6-9.6 years
40%
9.6-14.4 years
15%
Over 14.4 years

Building Permits

Issuance of building permits

Completed infrastructure

All connections active

Access ready

Paved access roads

Start of construction

Actual start of works

8/8

Summary and conclusions

Risk of delays

60%

of projects encounter delays

Average time

14.4-8.4

years for the full process

The most dramatic increase

400%-200%

in the change from agricultural to residential designation

Base agricultural land price range (minimum–maximum)

100-500%
National minimum
500-2,000%
National average
2,000-6,000%
National maximum

Main risk factors

40%
Public objections
30%
Infrastructure problems
20%
Legislative changes
10%
Other factors